Construction Progress

Stage 1

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Complete

Complete, with houses now constructed on most lots, including some display homes on the Glenelg Highway frontage.
Civil Construction PhaseStatus
Bulk EarthworkComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb and ChannelComplete
Electrical & NBNComplete
FootpathsComplete
AsphaltComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
TitlesIssued 27 March 2018
Inspection Phase 
ValuationsAvailable
Soil TestingAvailable

STAGE 2

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Complete

Housing construction is well underway in this stage and we are starting to see some examples of split level homes.
Civil Construction PhaseStatus
Bulk EarthworkComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb and ChannelComplete
Electrical & NBNComplete
FootpathsComplete
AsphaltComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
TitlesIssued 20 February 2019
Inspection Phase 
ValuationsAvailable
Soil TestingAvailable

STAGE 3

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Complete

House construction has commenced on these lots and we are excited to see the stage develop. We look forward to seeing more house builds commence in the New Year.
Civil Construction PhaseStatus
Bulk EarthworkComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb and ChannelComplete
Electrical & NBNComplete
FootpathsComplete
AsphaltComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
TitlesIssued 29 April 2020
Inspection Phase 
ValuationsAvailable
Soil TestingAvailable

STAGE 4

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Complete

This stage is mostly built out with more residents now calling Pinnacle home.
Civil Construction PhaseStatus
Bulk EarthworkComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb and ChannelComplete
Electrical & NBNComplete
FootpathsComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
TitlesIssued 20 September 2019
Inspection Phase 
ValuationsAvailable
Soil TestingAvailable

STAGE 5

(Lots 508 - 546)

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Complete

Some houses are about to commence construction and we look forward to seeing the streets take shape. Street tree planting is scheduled for April 2021, when the weather will start to cool.
Civil Construction PhaseStatus
Bulk EarthworksComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb & ChannelComplete
Electrical & NBNComplete
FootpathsComplete
AsphaltComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
TitlesIssued 16 September 2020
Inspection Phase 
ValuationAvailable
Soil TestingAvailable

STAGE 5A

(Lots 501-507)

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Complete

Titles have now been received for this stage and settlements are to commence in the last week of February 2021. With the issue of titles, the intersection of Kensington Boulevard with the Glenelg Highway will now be opened, allowing direct access into and out of Pinnacle from the Glenelg Highway.  Street tree planting is anticipated April 2021.
Civil Construction Phase Status
Bulk Earthworks Complete
Drainage Complete
Sewer Complete
Water & Gas Services Complete
Road Boxing, Kerb & Channel Complete
Electrical & NBN Complete
Footpaths Complete
Asphalt Complete
Signage & Topsoil Complete
Title Registration Phase
Practical Completion Complete
Statement of Compliance Complete
Titles Issued 8 February 2021
Inspection Phase
Valuation Available
Soil Testing Available*
*Access must be arranged with WVP prior to going onto site

Stage 7

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

COMPLETE

Titles have now been received and settlements are to commence mid-February 2021. We look forward to watching this stage develop over time. Street tree planting is anticipated April 2021.
Civil Construction Phase Status
Bulk Earthworks Complete
Drainage Complete
Sewer Complete
Water & Gas Services Complete
Road Boxing, Kerb & Channel Complete
Electrical & NBN Complete
Footpaths Complete
Asphalt Complete
Signage & Topsoil Complete
Title Registration Phase
Practical Completion Complete
Statement of Compliance Complete
Titles Issued 2 February 2021
Inspection Phase
Valuation Available
Soil Testing Available

Stage 8

0%

0%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Forecast Completion: 4th Quarter 2021

This stage has just been released for sale, with its construction due to commence 2nd quarter 2021. At this time titles are anticipated 4th quarter 2021.
Civil Construction Phase Status
Bulk Earthworks To Be Commenced
Drainage To Be Commenced
Sewer To Be Commenced
Water & Gas Services To Be Commenced
Road Boxing, Kerb & Channel To Be Commenced
Electrical & NBN To Be Commenced
Asphalt To Be Commenced
Signage & Topsoil To Be Commenced
Title Registration Phase
Practical Completion Forecast 4th Qtr 2021
Statement of Compliance Forecast 4th Qtr 2021
Titles and Settlement Forecast 4th Qtr 2021
Inspection Phase
Valuation Forecast 4th Qtr 2021
Soil Testing Forecast 4th Qtr 2021

Stage 9

20%

0%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Forecast Completion: Mid-2021

Drainage works are nearing completion and good headway has been made with earthworks and sewer works. This stage will start to take shape over the coming weeks with road boxing underway. At this time we are on-track for titles mid-2021.
Civil Construction PhaseStatus
Bulk EarthworksIn Progress
DrainageIn Progress
SewerIn Progress
Water & Gas ServicesTo Be Commenced
Road Boxing, Kerb & ChannelIn Progress
Electrical & NBNTo Be Commenced
AsphaltTo Be Commenced
Signage & TopsoilTo Be Commenced
Title Registration Phase 
Practical CompletionForecast 3rd Qtr 2021
Statement of ComplianceForecast 3rd Qtr 2021
Titles and SettlementForecast 3rd Qtr 2021
Inspection Phase 
ValuationForecast 3rd Qtr 2021
Soil TestingForecast 3rd Qtr 2021

Reserve

Shared path works on the western side of Kensington Boulevard extending from the Glenelg Highway to the southern edge of Stage 5 are complete. That path provides a connection to the shared path along the southern side of Kensington Boulevard heading east and will ultimately extend along the drainage corridor and through the future reserve in the southern portion of Pinnacle providing for a great walking/exercise trail. Landscape works along the northern section of the reserve surrounding the completed shared path are anticipated to commence in April 2021.