Construction Progress

INFRASTRUCTURE AND RESERVE

Whilst civil construction has been paused at Pinnacle, we are working with authorities and other developers in the area to deliver critical service infrastructure to enable the continued rollout of Pinnacle.

A further temporary sewer pump station will be required to cater for future residents within Pinnacle and nearby estates and construction on this and ancillary pipelines will be shortly commenced.

At its 22 February 2023, Council meeting, the City of Ballarat resolved to bring forward funds to deliver one of the wetland retarding basins within the 22 hectares of parkland in Pinnacle. Whilst this resolution will see the delivery of part of the critical drainage infrastructure in the shorter term, there are still some matters that need to be worked through prior to Council being able to get on the ground and deliver that basin. We do however hope to see works commence on this wetland later in 2023.

Whilst that Council resolution is the first step in progressing works within the Pinnacle parkland, unfortunately, until that basin and a further basin to its south are delivered, we cannot construct the playground in the parkland (to avoid damage to that space given it is between the two and to ensure play activities are removed from work zones). The delivery of the second wetland retarding basin however will require an amendment to the Ballarat West Development Contributions Plan, which is currently being prepared by Council and in which, unfortunately, is a lengthy process. As such, at this time, the timing is unknown. However given we are now getting greater certainty on the detailed design of the wetlands, we will now be able to develop our plans for the Pinnacle playground so as it can be delivered soon after the required drainage infrastructure is in place. Please rest assured that we are committed to delivering the playground when practicably possible.

Further updates will be provided once available.

Stage 1 – Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 2 – COMPLETE

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 3 – COMPLETE

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 4 – COMPLETE

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 5 – COMPLETE

(Lots 508 - 546)

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 5A – COMPLETE

(Lots 501-507)

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

STAGE 6 – COMPLETE

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

COMPLETE

We are excited to see a number of dwellings under construction on this stage.

There are a few lots still available, so get in quick to secure a titled lot now and start building your dream home!

Civil Construction PhaseStatus
Bulk EarthworksComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb & ChannelComplete
Electrical & NBNComplete
FootpathsComplete
AsphaltComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
TitlesIssued 23 Feb 2022
Inspection Phase 
ValuationAvailable
Soil TestingAvailable
 

Stage 7 - Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Stage 8 - Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Complete

House construction has commenced in this stage, and street trees have been planted. We look forward to watching this stage evolve.

Civil Construction PhaseStatus
Bulk EarthworksComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb & ChannelComplete
Electrical & NBNComplete
FootpathsComplete
AsphaltComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
Titles and SettlementIssued 5 August 2021
Inspection Phase 
ValuationAvailable
Soil TestingAvailable

Stage 9 - Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Complete

It is exciting to see housing under construction and street trees installed. We look forward to watching this stage evolve.
Civil Construction PhaseStatus
Bulk EarthworksComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb & ChannelComplete
Electrical & NBNComplete
FootpathsComplete
AsphaltComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
TitlesIssued 27 May 2021
Inspection Phase 
ValuationAvailable
Soil TestingAvailable
 

Stage 11 - Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Completed

House construction has commenced on a number of lots in this stage and it is really starting to take shape. We look forward to seeing these completed in the coming months.
 
Civil Construction PhaseStatus
Bulk EarthworksComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb & ChannelComplete
Electrical & NBNComplete
FootpathsComplete
AsphaltComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
Titles and SettlementIssued 29 October 2021
Inspection Phase 
ValuationAvailable
Soil TestingAvailable

Stage 10 - CompLete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

COMPLETE

 

Settlements have now commenced in this stage, and we look forward to seeing house construction commenced on these amazingly located lots in the coming months.

There are still a couple of lots available in this stage, so if you are looking to build your dream home now on lots within walking distance to a great range of amenities, get in quick!

Civil Construction PhaseStatus
Bulk EarthworksComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb & ChannelComplete
Electrical & NBNComplete
Footpaths Complete
Asphalt Complete
Signage & Topsoil Complete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
Titles and SettlementIssued 21 July 2022
Inspection Phase 
ValuationAvailable
Soil TestingAvailable

 

 
 
 
 

Stage 7B Waterfront - Complete

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

COMPLETE

Titles have now been issued for the Waterfront release and we are excited that settlements on lots in this stage will soon commence.

For those of you wanting to build in the shorter term, there are titled prime lots still available in this stage along the future park and wetland reserve. Valuers can access the stage with prior arrangements from the civil contractor to get your finance sorted today. Don’t miss out!

Civil Construction PhaseStatus
Bulk EarthworksComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb & ChannelComplete
Electrical & NBNComplete
FootpathsComplete
AsphaltComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
Titles and SettlementIssued 14 November 2022
Inspection Phase 
ValuationAvailable*
Soil TestingFollowing settlement or with prior Developer approval*

* Valuer access allowed with prior arrangement with civil contractor. Any access for soil testing must be following receipt of written developer approval if prior to settlement.