Construction Progress

Stage 1

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Complete

Complete, with houses now constructed on most lots.

STAGE 2

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Complete

Housing construction is well underway in this stage and we are starting to see some examples of split level homes.

STAGE 3

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Complete

This stage is starting to take shape with more housing construction underway. We look forward to seeing more residents moving into Pinnacle in the near future.

STAGE 4

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Complete

This stage is mostly built out with more residents now calling Pinnacle home.

STAGE 5

(Lots 508 - 546)

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Complete

A number of houses are now under construction in this stage, which is exciting to see. Street tree planting is scheduled for May 2021.
Civil Construction PhaseStatus
Bulk EarthworksComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb & ChannelComplete
Electrical & NBNComplete
FootpathsComplete
AsphaltComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
TitlesIssued 16 September 2020
Inspection Phase 
ValuationAvailable
Soil TestingAvailable

STAGE 5A

(Lots 501-507)

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Complete

With titles issued and settlements underway, we expect to see some development occurring on these lots in the near future. Street tree planting is scheduled for May 2021.

Civil Construction PhaseStatus
Bulk EarthworksComplete
DrainageComplete
SewerComplete
Water & Gas ServicesComplete
Road Boxing, Kerb & ChannelComplete
Electrical & NBNComplete
FootpathsComplete
AsphaltComplete
Signage & TopsoilComplete
Title Registration Phase 
Practical CompletionComplete
Statement of ComplianceComplete
TitlesIssued 8 February 2021
Inspection Phase 
ValuationAvailable
Soil TestingAvailable

Stage 7

100%

100%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

COMPLETE

House construction is commencing on lots within this stage and we look forward to seeing it take shape.  Street tree planting is scheduled for May 2021.
Civil Construction Phase Status
Bulk Earthworks Complete
Drainage Complete
Sewer Complete
Water & Gas Services Complete
Road Boxing, Kerb & Channel Complete
Electrical & NBN Complete
Footpaths Complete
Asphalt Complete
Signage & Topsoil Complete
Title Registration Phase
Practical Completion Complete
Statement of Compliance Complete
Titles Issued 2 February 2021
Inspection Phase
Valuation Available
Soil Testing Available

Stage 8

30%

0%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Forecast Completion: September 2021

Sewer and drainage is nearly complete and kerb and channelling has commenced, with this stage starting to take shape. Footpath works will begin in coming weeks, with electrical works scheduled for the start of June 2021. At this time, completion of the works is anticipated around the start of August 2021, with audits to follow.
Civil Construction Phase Status
Bulk Earthworks Complete
Drainage In Progress
Sewer In Progress
Water & Gas Services In Progress
Road Boxing, Kerb & Channel In Progress
Electrical & NBN To Be Commenced
Footpaths To Be Commenced
Asphalt To Be Commenced
Signage & Topsoil To Be Commenced
Title Registration Phase
Practical Completion Forecast August 2021
Statement of Compliance Forecast August 2021
Titles and Settlement Forecast September 2021
Inspection Phase
Valuation Forecast August 2021
Soil Testing Forecast September 2021

Stage 9

100%

35%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Forecast Completion: May 2021

With civil works complete, audits have been undertaken and are complete. We await final authority sign-offs for the issue of a statement of compliance, which is expected the week of 17 May 2021. The plan of subdivision will be lodged soon after, with settlements anticipated early June 2021.
Civil Construction Phase Status
Bulk Earthworks Complete
Drainage Complete
Sewer Complete
Water & Gas Services Complete
Road Boxing, Kerb & Channel Complete
Electrical & NBN Complete
Footpaths Complete
Asphalt Complete
Signage & Topsoil Complete
Title Registration Phase
Practical Completion April 2021
Statement of Compliance Forecast May 17 2021
Titles and Settlement Forecast May 2021
Inspection Phase
Valuation Available*
Soil Testing Available*
*Access will be confirmed prior to this date

Stage 11

10%

0%

CIVIL CONSTRUCTION PROGRESS

TITLE REGISTRATION PROGRESS

Forecast Completion: December 2021

This stage is soon to be released to the market, with early works having been undertaken to allow for the stage to be constructed during the wetter months.  Keep an eye out on our website for the upcoming stage release.
Civil Construction Phase Status
Bulk Earthworks In Progress
Drainage To Be Commenced
Sewer To Be Commenced
Water & Gas Services To Be Commenced
Road Boxing, Kerb & Channel In Progress
Electrical & NBN To Be Commenced
Footpaths To Be Commenced
Asphalt To Be Commenced
Signage & Topsoil To Be Commenced
Title Registration Phase
Practical Completion Forecast November 2021
Statement of Compliance Forecast November 2021
Titles and Settlement Forecast December 2021
Inspection Phase
Valuation Forecast Novemver 2021
Soil Testing Forecast Nov/Dec 2021

Reserve

 

Landscape plans are being finalised for works to commence within the linear reserve as soon as possible, with it anticipated the commencement of these works will now be pushed back until May 2021.  This will see the first section of the linear reserve between the Glenelg Highway and Kensington Boulevard (heading east) delivered.  This narrower section of the reserve will provide opportunities for passive recreation, such as picnics.